Major Electrical Upgrade with New Main Switchboard and Infrastructure Integration

Work Completed

As part of a major works project for this site new electrical infrastructure including supply authority distribution network modifications, new consumers mains a new site main switchroom, mains switchboard and site electrical distribution system was required due to the increase in electrical load being caused by new equipment within the building.

Existing store areas were demolished and a new 2hr fire-rated main switchroom was built to house the new main switchboard and site metering.

Excavation works associated with new underground conduits and consumers mains were undertaken along with new tray work throughout the building as part of the new electrical distribution system.

Co-ordination with the supply authority and level 1 ASP were undertaken to complete street network augmentation works enabling the site to obtain a larger capacity service required under the project.

All site and network shutdowns were coordinated with relevant stakeholders along with required temporary services to enable to successful cutover of all new mains and site distribution cabling while the facility continued to operate without disruption.

The site’s existing standby generator plant and associated control system were modified to operate in conjunction with the new main switchboard which was also successfully cut over and commissioned as part of the project.

New Exit and Emergency lighting was also installed within the site as part of the project. 

Recent Work

Discover Our Latest Project Highlights

Welcome to GNM Industries' Project Showcase. Specialising in a vast array of sophisticated engineering solutions, we excel in delivering high-end projects across multiple domains. Our expertise ranges from intricate HVAC system renewals, innovative electrical infrastructure upgrades, to advanced air conditioning and ductwork enhancements. We pride ourselves on our ability to handle complex renovations like Standby Generator Plant (SGP) upgrades and sustainable building transformations. Our projects demonstrate a keen focus on integrating eco-friendly practices with state-of-the-art technology. Discover how we bring efficiency, sustainability, and cutting-edge design to every undertaking, ensuring each project is a testament to our commitment to excellence and client satisfaction. Explore our diverse project portfolio that reflects our dedication to modernising, upgrading, and transforming facilities to meet the demands of a dynamic world.

Integrated HVAC Upgrade

Engaged for a major HVAC upgrade, we collaborated with the client’s team for detailed planning and execution. Temporary systems ensured uninterrupted operation during the complex process of splitting and upgrading the facility's HVAC system. Comprehensive works included new installations, system enhancements, and integrating advanced control systems, ensuring efficiency and modernisation.

Efficient AC Upgrade

The existing main air conditioning system serving this facility was at the end of its maintainable life span. With this in mind and additional future load increases planned for the site we were engaged to provide both design and construction services to provide a solution for the upgrade of the aging plant along with augmenting the existing supplementary units into the new system.

Standby Generator Plant (SGP) Capacity Enhancement

Our team expertly executed the Standby Generator Plant (SGP) Upgrade, significantly boosting power reliability and capacity. The project entailed detailed audits, temporary solutions, and a new Cummins generator installation, all within a tight space and timeframe. This upgrade exemplifies our commitment to advanced, efficient power solutions.

Complete HVAC System Renewal

This project successfully involved the full replacement of the main air conditioning system, upgrading to high-efficiency Temperzone units. Including asbestos removal, new ductwork, and a custom mechanical services switchboard, the project concluded with system testing and balancing, exemplifying our expertise in modern HVAC solutions.

Ductwork Upgrade

This project skillfully enhanced the ductwork system for a data floor, integrating new outlets for equipment suites. Our proposal included ductwork redesign, dropper, damper, and grille installation, with meticulous air and temperature testing for optimal airflow, demonstrating our commitment to innovative and efficient air distribution solutions.

Switchboard and Electrical Infrastructure Transformation

This major project involved upgrading electrical infrastructure, including a new main switchroom and switchboard, to accommodate increased loads from new equipment. Work included building a fire-rated switchroom, excavating for conduits, and coordinating with supply authorities, culminating in a seamless integration of new emergency lighting and generator systems.

Empowering Tomorrow:

GNM Industries Illuminate NSW Government Schools with Solar Panel Installations

GNM Industries has implemented custom solar solutions in six NSW public schools as part of a government initiative, focusing on environmental responsibility and cost savings. These installations, featuring high-efficiency panels and energy storage, optimise energy efficiency and integrate with existing infrastructure, marking a significant step towards sustainability and reduced energy costs.

Empowering Businesses:

 Solar Panel and Battery Installation Drives Sustainable Solutions

GNM Industries has implemented custom solar solutions in six NSW public schools as part of a government initiative, focusing on environmental responsibility and cost savings. These installations, featuring high-efficiency panels and energy storage, optimise energy efficiency and integrate with existing infrastructure, marking a significant step towards sustainability and reduced energy costs.